Trianel Erneuerbare Energien has begun construction of its first wind farm in Schleswig-Holstein. Since late August 2025, groundwork and access road development have been underway in the Plön district near the communities of Tasdorf, Großharrie, and Bönebüttel.
The site is located in a designated wind priority area with favourable conditions and high expected yields. Eight Nordex N149/5.X turbines will be installed, with an annual generation capacity of up to 110 million kilowatt hours, enough to supply around 30,000 households. The Trianel Windpark Tasdorf is being developed in cooperation with ABO Energy and Trianel Energieprojekte. Commissioning is planned for summer 2027.